Upcoming opportunities for local and regional contractors to support the construction of the EPIC Campus project.

Capability Details Estimated Contract Value Start Date
Scaffolding Build and monitor. Estimated requirement of 30 people for roughly a year in the first instance. £500,000.00 ASAP
Brickwork/Blockwork Bricklaying. References and certifications will be requested at ITT/PQQ phase. £700,000.00 – £800,000.00 Sep‑26
Drylining Supply & Install. Estimated 20–50 people required. £2,000,000.00 Sep‑26
Soft Flooring 16 weeks manufacturing + 4 weeks on site. <£250,000.00 Feb‑27
Painting & Decorating 16 weeks manufacturing + 4 weeks on site. <£500,000.00 Jan‑27
Joinery – Various contracts internal doors, ironmongery, timber acoustic raised floors, skirtings etc. £700,000.00 Jan‑27
Fitted Furniture – Various contracts General fittings, furnishings & equipment. Main entrance desk. Kitchenette Unknown Mar 27
Tiling 16 weeks manufacturing + 4 weeks on site. Installation Q3/Q4 2027. <£500,000.00 Mar‑27
Signage – Various contracts Signs & notices (Wayfinding). Statutory signage. Building signage £100,000.00 Sep – Dec 27
Feature Wall – Printed Graphics TBC, Awaiting Design <£250,000.00 TBC
Builders Merchants Any local or regional national branch to be recommended. Unknown ASAP
Internal Doors & IPS Systems 16 weeks manufacturing + 4 weeks on site. Installation Q3/Q4 2027. £1,500,000.00 May‑27

Interested in bidding?

Register your business or log in to view tender documentation and submit expressions of interest.

Register Your Business Already registered? Log In Here Express Interest in a Specific Opportunity

← Back to EPIC Campus Project Page